CMA Inter Suggested Answers | Dec 25 Paper 9 Operations Management and Strategic Management
Table of contents
CMA Inter Dec 25 Suggested Answer Other Subjects Blogs :
(i) With reference to the operations of RN Ltd., a manufacturing company, one of the important decisions is “How to reach the products to the Customers”? Which one of the following is related to this?
(ii) The ISO standard associated with “Quality Management and Quality System Elements – Guidelines” is
(iii) In a particular plant there are 15 workers manufacturing a single product and the output per month consisting of 25 days of that particular product is 450 units. How much is the monthly productivity?
(iv) In which phase of the product life cycle the objective is to hold the existing customers and create new customers?
(v) Gantt Chart is a principal tool used in –
Choice 'A' is correct as--
Gantt Chart is a principal tool used in:
Scheduling.
A Gantt chart is a visual representation of a project schedule, showing the start and finish dates of various elements of a project. It is widely used for scheduling tasks in project management, helping to track progress and allocate resources efficiently
(vi) Which one of the following processes of Project Quality Management assures the existence and effectiveness of process and procedures tools?
(vii) The Slack Time of Tail Event of Activity – D of a Project is 1 day. If the total Float and Free Float of the activity D are 8 days and 6 days respectively, the Independent Float of D will be
(viii) Which one of the following is not the primary constraint of a project?
(ix) Preventive Maintenance is useful in reducing
Choice 'B' is correct as--
Preventive maintenance is useful in reducing:
Shutdown Cost.
Preventive maintenance helps in identifying and addressing potential issues before they lead to equipment failure, thereby minimizing unplanned downtimes and the associated costs of production halts. This reduces the likelihood of costly shutdowns and ensures smoother, continuous operations.
(x) A workshop of Gear Tech (I) Ltd. has 20 nos. of identical machines. From the failure pattern of the machines, it is calculated that the expected time before failure is 4 months. It costs ₹500 to attend a failure machine and rectify the same. What will be the yearly cost of servicing the broken-down machines?
(xi) The Strategy which is about how to compete successfully in particular markets is:
(xii) Which among the following provide(s) the standards for performance appraisal?
Choice 'D' is correct as--
Objectives act as the clear, measurable benchmarks against which employee performance is evaluated.
They provide specific targets that help assess how well an individual has performed during a given period.
Mission, vision, and values guide overall organisational direction, but they do not offer quantifiable standards for appraisal.
Since performance appraisal requires concrete and assessable criteria, objectives directly serve this purpose.
Therefore, objectives provide the standards for performance appraisal.
(xiii) In the “SMART goal framework” the letter “S” stands for:
(xiv) Environment is ________
Choice 'D' is correct as--
The business environment is considered complex because it consists of many interconnected factors.
It is multi-faceted since the same event can affect different organisations in different ways.
It is also dynamic because changes occur continuously due to technology, competition and policies.
All these characteristics together define the nature of the business environment.
Hence, the correct answer is option D.
Choice 'D' is correct as--
BPR (Business Process Reengineering) focuses on redesigning processes from the ground up to achieve dramatic improvements.
It does not limit itself to just speed, efficiency, or quality—it enhances all major performance dimensions simultaneously.
Through radical restructuring, organisations achieve faster processes, higher productivity, and better-quality outcomes.
Thus, BPR results in major gains in efficiency, quality, and speed, making option D the most appropriate answer.
“Recent trends in Production and Operations Management relate to global competition” – With reference to this Statement, Align seven of the recent trends in Production and Operations Management.
Recent trends in production / operations management relate to global competition and the impact it has on manufacturing firms. Some of the recent trends are :
(1) Global Market Place : Globalisation of business has compelled many manufacturing firms to have operations in many countries where they have certain economic advantages. This has resulted in a steep increase in the level of competition among manufacturing firms throughout the world.
(2) Production / Operations Strategy : More and more firms are recognizing the importance of production / operations strategy for the overall success of their business and the necessity for relating it to their overall business strategy.
(3) Total Quality Management (TQM) : TQM approach has been adopted by many firms to achieve customer satisfaction by a never-ending quest for improving the quality of goods and services.
(4) Flexibility : The ability to adapt quickly to changes in volume of demand, in the product mix demanded, and in product design or in delivery schedules, has become a major competitive strategy and a competitive advantage to the firms. This is sometimes called as agile manufacturing.
(5) Time Reduction : Reduction of manufacturing cycle time and speed to market for a new product provide competitive edge to a firm over other firms. When companies can provide products at the same price and quality, quicker delivery (short lead times) provide one firm competitive edge over the other.
(6) Technology : Advances in technology have led to a vast array of new products, new processes and new materials and components. Automation, computerisation, information and communication technologies have revolutionised the way companies operate.
(7) Worker Involvement : The recent trend is to assign responsibility for decision making and problem solving to the lower levels in the organisation. This is known as employee involvement and empowerment.
Examples of worker involvement are quality circles and use of work teams or quality improvement teams.
(8) Re-engineering : This involves drastic measures or break-through improvements to improve the performance of a firm. It involves the concept of clean-slate approach or starting from scratch in redesigning the business processes.
(9) Environmental Issues : Today's production managers are concerned more and more with pollution control and waste disposal which are key issues in protection of environment and social responsibility.
(10) Corporate Downsizing (or Right Sizing) : Downsizing or right sizing has been forced on firms to shed their obesity. This has become necessary due to competition, lowering productivity, need for improved profit and for higher dividend payment to shareholders.
(11) Supply - Chain Management : Management of supply-chain, from suppliers to final customers reduces the cost of transportation, warehousing and distribution throughout the supply chain.
(12) Lean Production : Production systems have become lean production systems which use minimal amounts of resources to produce a high volume of high quality goods with some variety.
“Likewise, the Business Organisations and Human Beings, each product has a life that goes through various phases or cycles” – In this Context, Analyze and Align the Prospective Phases of Product Life Cycle.
STEEL MAX Ltd. invested in a precision laser cutting machine with a purchase cost of ₹5,00,000 and an installation cost of ₹50,000. The resale value remains fixed at ₹60,000 throughout its life. However, maintenance costs increase with age. The management is analyzing over a 10-year span to determine the most cost-effective replacement year.
|
Year |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
|
Maintenance Cost (₹ in Thousand) |
10 |
15 |
22 |
30 |
45 |
60 |
80 |
110 |
145 |
185 |
(Ignore Cost of Money)
Required :
(i) Analyze Average Annual Cost of replacement of cutting machine for each year.
(ii) Assess and Identify after how many years should Steel Max Ltd., replace the cutting machine on economic considerations.
FRESHWEAR Clothing Co. shifted its marketing strategy to focus heavily on digital outreach. The management wants to examine how their monthly sales are influenced by the number of social media ad impressions (in Crore). They collected the following data over the last six months:
|
Month |
Ad. Impressions (in Crore) (X) |
Sales (₹ in Crore) (Y) |
|
Jan |
1 |
18 |
|
Feb |
2 |
23 |
|
Mar |
4 |
32 |
|
Apr |
3 |
28 |
|
May |
10 |
38 |
|
Jun |
4 |
29 |
Required :
(i) Fit a linear regression of Sales (Y) on Ad. Impressions (X)
(ii) If FRESHWEAR plans to run a campaign that reaches 5 Crore (Nos.) impressions, forecast their expected monthly sales using simple linear regression
AUTO BUILD Ltd. specializes in high-precision car components. The production manager wants to assign four skilled workers – R, A, N and Z – to four complex assembly jobs: GA, BS, EM and EF. Each worker has different time efficiencies for each job (in hours). The goal is to assign one job to each worker to minimize the total time required.
|
|
Jobes |
|||
|
Workes |
GA |
BS |
EM |
EF |
|
R |
10 |
12 |
16 |
17 |
|
A |
9 |
12 |
14 |
14 |
|
N |
12 |
14 |
15 |
16 |
|
Z |
10 |
11 |
12 |
13 |
Required :
(i) Analyze and Assign the appropriate job to each worker to minimize the total work hours.
(ii) Assess what is the minimum total time required to finish the jobs.
QUICKKART COURIERS Ltd., a growing logistics firm, wants to simulate their parcel delivery times during monsoon to assess variability and potential delays. They have collected historical data and created a probability distribution of delivery time (in minutes).
|
Delivery Time (minutes) |
15 |
20 |
25 |
30 |
35 |
|
Probability |
0.10 |
0.20 |
0.35 |
0.25 |
0.10 |
The following two-digit random numbers are to be used to simulate delivery for 10 parcels.
|
Random Number |
04 |
19 |
33 |
46 |
60 |
74 |
85 |
91 |
23 |
38 |
ROTIS Ltd., a manufacturing company produces two types of products: Super and Regular.
Resource requirements for production are given below in the table.
There are 16000 hours of assembly worker hours, 7000 hours of paint time and 3000 hours of inspection time available per week.
Regular customers will demand at least 500 units of the Regular type and 200 units of Super type.
|
Product Type |
Profit per unit (₹) |
Assembly time (Hrs.) |
Paint time (Hrs.) |
Inspection time (Hrs.) |
|
Regular |
50 |
12 |
8 |
2 |
|
Super |
75 |
16 |
9 |
2 |
Required :
Develop a mathematical formulation of L.P.P. to determine how many products should be produced to maximize the profit.
(You are not required to solve the LPP.)
SWIFT TRANS LOGISTICS Ltd. is planning a distribution centre expansion.
The operation manager has split their schedule of implementation into the following 6 activities and have estimated time duration (in weeks) under 3 scenarios as under:
(Time in Weeks)
|
Activity and Identification |
Optimistic time estimate (t₀) |
Pessimistic time estimate (tₚ) |
Most likely time estimate (tₘ) |
|
A (1–2) |
1 |
5 |
3 |
|
B (1–3) |
3 |
3 |
3 |
|
C (2–4) |
2 |
8 |
5 |
|
D (2–5) |
3 |
13 |
7 |
|
E (3–5) |
2 |
9 |
6 |
|
F (4–5) |
5 |
11 |
8 |
Required :
(i) Assess the expected duration (in weeks) for each activity.
(ii) Design the PERT Network Diagram and indicate all paths through it.
(iii) Identify the Critical Path and its duration (in weeks).
(iv) Analyze and indicate the variance of each activity.
“The goal is to achieve quantity and quality of effort between individuals’ and the team” – In this context, analyze and append the details regarding the SMART goal framework to create organizational objectives
“BLOCKCHAIN is a shared, immutable ledger that facilitates the process of recording transactions and tracking assets in a business network” – In this context, Examine and Align the important components of a BlockChain.
Summarize, in brief, a detailed explanation of the PESTEL Framework
“The Formal Strategic Planning process has five main steps” – In accordance to this statement, Examine and Align the respective steps of Strategic Planning process.
The formal strategic planning process has five main steps:
i. Select the corporate mission and major corporate goals:
The first component of the strategic planning process is crafting the organisation’s mission statement, which provides the framework or context within which strategies are formulated. A mission statement has four maincomponents: a statement of its reason for existence which is normally referred to asthe mission; a statement ofsome desired future state, usually referred to as the vision; a statement of the key values that the organisation is committed to; and a statement of major goals.
ii. Analyse the organisation’s external competitive environment to identify opportunities and threats:
The second component of the strategic planning process is an analysis of the organisation’s external operatingenvironment. The essential purpose of the external analysis is to identify strategic opportunities and threats within the organisation’s operating environment that will affect how it pursues its mission. Three interrelatedenvironments should be examined when undertaking an external analysis: the industry environment inwhich the company operates, the country or national environment and the wider socioeconomic or macro environment.
iii. Analyse the organisation’s internal operating environment to identify the organisation’s strengths andweaknesses:
Internal analysis, the third component of the strategic planning process, focuses on reviewing the resources, capabilities, and competencies of a company. The goal is to identify the strengths and weaknesses of the company. The next component of strategic thinking requires the generation of a series ofstrategic alternatives,or choices of future strategiesto pursue, given the company’sinternalstrengths and weaknesses and its externalopportunities and threats. The comparison of strengths, weaknesses, opportunities, and threats is normally referred to as a SWOT analysis. More generally, the goal of a SWOT analysis is to create, affirm, or fine-tune
a company-specific business model that will best align, fit, or match a company’sresources and capabilities tothe demands of the environment in which it operates.
iv. Select strategies:
Managers select strategies that build on the organisation’s strengths and correct its weaknesses in order to take advantage of external opportunities and counter external threats. In order to select the right strategies managers compare and contrast the various alternative possible strategies against each other and then identifythe set of strategies that will create and sustain a competitive advantage. It is very important for the strategic managers to keep in mind that the strategies selected should be consistent with the mission and major goals ofthe organisation. They should be congruent and constitute a viable business model.
i. Implement the strategies:
In order to achieve a competitive advantage and increase profitability managers must put those strategies selected into action. Strategy implementation involves taking actions at the functional, business, and corporatelevels to execute a strategic plan.
Strategy implementation also entails designing the best organisation structure and the best culture and control systems to put a chosen strategy into action. In addition, senior managers need to put a governance system in placeto make sure that all within the organisation act in a mannerthat is not only consistent with maximizing profitabilityand profit growth, but also legal
and ethical.
The Feedback Loop:
The strategy planning process is a continuous process and the feedback loop indicates that strategic planning neverends. In order to determine the extent to which strategic goals and objectives are actually being achieved, and to what degree competitive advantage is being created and sustained execution of the strategy must be monitored. This information and knowledge is returned to the corporate level through feedback loops, and becomes the input for the next round of strategy formulation and implementation. Top managers can then decide whether to reaffirmthe existing business model and the existing strategies and goals, or suggest
changes for the future.
What do you infer from Project-based Structures? Align the advantages and disadvantages of project based structures.
A project-based structure is one where teams are created, undertake the work and are then dissolved. This can be particularly appropriate for organisations that deliver large and expensive goods or services (civil engineering, information systems, films) or those delivering time-limited events (conferences, sporting events or consulting engagements). The organisation structure is a constantly changing collection of project teams created, steered and glued together loosely by a small corporate group. Many organisations use such teams in a more ad hoc way to complement the ‘main’ structure. For example, taskforces are set up to make progress on new elements of strategy or to provide momentum where the regular structure of the organisation is not effective.
Advantages of Project-based structures
Disadvantages of Project-based structures
Overall, project-based structures have been growing in importance because of their inherent flexibility. Such flexibility can be vital in a fast-moving world where individual knowledge and competences need to be redeployed and integrated quickly and in novel ways.
Structural choice depends on the strategic challenges the organisation faces. In reality, few organisations adopt a structure that is just like one of the pure structural types discussed above. Structures often blend different types and have to be tailor-made to the particular mix of challenges facing the organisation. Michael Goold and Andrew Campbell provide nine design tests against which to check specific tailor-made structural solutions. The first four tests stress fit with the key objectives and constraints of the organisation:
(i) Critically Assess important reasons that lead an organization to undertake Business Process Re-engineering.
(ii) Discuss four concerns while implementing the Business Process Re-engineering program.
Ruchika Ma'am has been a meritorious student throughout her student life. She is one of those who did not study from exam point of view or out of fear but because of the fact that she JUST LOVED STUDYING. When she says - love what you study, it has a deeper meaning.
She believes - "When you study, you get wise, you obtain knowledge. A knowledge that helps you in real life, in solving problems, finding opportunities. Implement what you study". She has a huge affinity for the Law Subject in particular and always encourages student to - "STUDY FROM THE BARE ACT, MAKE YOUR OWN INTERPRETATIONS". A rare practice that you will find in her video lectures as well.
She specializes in theory subjects - Law and Auditing.
Yash Sir (As students call him fondly) is not a teacher per se. He is a story teller who specializes in simplifying things, connecting the dots and building a story behind everything he teaches. A firm believer of Real Teaching, according to him - "Real Teaching is not teaching standard methods but giving the power to students to develop his own methods".
He cleared his CA Finals in May 2011 and has been into teaching since. He started teaching CA, CS, 11th, 12th, B.Com, M.Com students in an offline mode until 2016 when Konceptca was launched. One of the pioneers in Online Education, he believes in providing a learning experience which is NEAT, SMOOTH and AFFORDABLE.
He specializes in practical subjects – Accounting, Costing, Taxation, Financial Management. With over 12 years of teaching experience (Online as well as Offline), he SURELY KNOWS IT ALL.